Renovation week, 21st September 2015.

Renovation week will consist of hollow tining the greens with 8mm hollow tines down to a depth of 2″ then dressed with 30 tons of Ruffords no3 topdressing and 2tons of zeolite with resources concentrated to 2,3,4,5,10,11 and 13th. Verti-draining/solid tining down to 7″.
◾Monday: Hollow tining greens with possible 3 temporary greens in place.
◾Tuesday: Hollow tining greens then verti-draining will commence with possible 3 temporary greens in place.
◾Wednesday: Verti-draining greens and topdressing applied and brushed in, 2 temporary greens in place.
◾Thursday: Topdressing applied and brushed in, 2 temporary greens in place.
◾Friday: Course presentation.